Scheduling Jobs on a Single Machine
You have \(n\) tasks, and you need to find an order to execute them with minimal cost. The \(i\)-th task takes time \(t_i\), and waiting for time \(t\) for the \(i\)-th task incurs a cost of \(f_i(t)\).
Formally, given \(n\) functions \(f_i\) and \(n\) numbers \(t_i\), find a permutation \(p\) that minimizes
Special Cost Functions
Linear Cost Functions
First, consider the case where all functions are linear, i.e., \(f_i(x)=c_ix+d_i\), where \(c_i\) is a non-negative integer. Obviously, we can sum the constant terms in advance, so the functions reduce to the form \(f_i(x)=c_ix\).
Consider two permutations \(p\) and \(p'\), where \(p'\) is obtained by swapping the \(i\)-th and \((i+1)\)-th elements of \(p\). Then
Thus, we can use the strategy of swapping if \(c_{p_i}t_{p_{i+1}}-c_{p_{i+1}}t_{p_i}>0\). Writing it as \(\dfrac{c_{p_i}}{t_{p_i}}>\dfrac{c_{p_{i+1}}}{t_{p_{i+1}}}\), it can be understood as sorting the permutation in ascending order of \(\dfrac{c_i}{t_i}\).
To handle this problem, our idea is to consider the changes after perturbation and greedily select the optimal solution.
Exponential Cost Functions
Consider cost functions of the form \(f_i(x)=c_i\mathrm{e}^{ax}\), where \(c_i\ge 0,a>0\).
We follow the previous idea and consider the cost change caused by swapping the \(i\)-th and \((i+1)\)-th elements. The resulting algorithm sorts the permutation in ascending order of \(\dfrac{1-\mathrm{e}^{at_i}}{c_i}\).
Identical Monotonic Functions
Consider the case where all \(f_i(x)\) are the same monotonic function. Then obviously, we sort the permutation in ascending order of \(t_i\).
Livshits–Kladov Theorem
The Livshits–Kladov theorem holds if and only if the cost functions fall into one of the following three cases:
- Linear functions: \(f_i(t) = c_it + d_i\), where \(c_i\ge 0\);
- Exponential functions: \(f_i(t) = c_i \mathrm{e}^{a t} + d_i\), where \(c_i,a>0\);
- Identical monotonic functions: \(f_i(t) = \phi(t)\), where \(\phi(t)\) is a monotonic function.
The theorem is proven under the assumption that the cost functions are sufficiently smooth (have third-order derivatives). In these three cases, the optimal solution to the problem can be obtained by simple sorting in \(O(n\log n)\) time.